All that brick is one week's work. They will finish the first one meter today and next week will start on the second meter. Then they put forms around the castillos (rebar) and pour them. Too bad they can't work for a few more months but the Canadian owners leave at the end of the month.
Showing posts with label brick. Show all posts
Showing posts with label brick. Show all posts
Saturday, January 16, 2016
Wednesday, January 13, 2016
Dala work last week
Last week was only about week five and the dala was finished all the way around. This week it's cleanup and starting laying brick on the back wall. Muy bien trabajo and everybody is happy except for the Presta Nombre from HELL.
Labels:
brick,
dala,
HELL.,
Presta Nombre,
wall
Thursday, April 18, 2013
Cleaning up the yard
I had a section of grass that seemed unable to recover mostly due to traffic and a dog that excavates to cool off so this is what we came up with. The problem with bricking it all is water drainage from the shed roof above so I decided on that gravel strip. If that area wasn't dirt it was mud and both getting tracked everywhere. This is going to be so much better.
For a long time I've talked about filling in the door in my front wall that was originally designed as a second entrance to the other lot. The lots won't ever be separated so it's only a window for my dog to bark at kids passing in the street. It wasn't very attractive and the metal requires upkeep. I ordered way too many bricks for the patio so Hugo said why not use them for the door. And he needed the work.
New patio with shed roof above
No dirt showing now
Hugo filling in the door
Tuesday, November 11, 2008
Weeks Six and Seven
They finished the walls to the two meter level and now it's time to tie it all together with a cement header (dala) all the way around. Today they will finish pouring the header on the two rooms in the back .... and them on to the front two rooms. We're also putting some of the electrical tubing in the dalas so the roof installation will have a few less to do. The routing of the wires is not what I would have chosen but unless I'm there all day to check ... and I've been feeling under the weather this week. Anything can be re-done by chipping away the cement and brick and that's what they rely one.
Beginning of week Six
Toward end of week Six
Week Seven and dalas (headers) are started
Rebar for dalas almost in place and cement forms starting
I added this foto from the end of week seven to show the headers with forms off
Building a small house on the Costalegre, Jalisco Mexico
Labels:
brick,
cement,
Costalegre,
dala,
header
Thursday, October 30, 2008
Putting up more walls - Week Five
This week we are finishing up the walls of two rooms of the four and putting up half walls of the last two. The half walls you see are one meter and they stop there so as to not put too much weight on the wet mortar
The second foto shows how the wooden forms are held in place for the castillos. They push a stick through the wet mortar as they lay brick (rather than drilling holes later) and use wire to attach the boards. The brick and smaller board make a lever to hold the forms close.
The bottom foto is how one of the neighbors brings out water from his place because the street water has been shut off for two days. Like siphoning gas out of a car, we suck on the hose and get 55 gallons mas o menos.
The second foto shows how the wooden forms are held in place for the castillos. They push a stick through the wet mortar as they lay brick (rather than drilling holes later) and use wire to attach the boards. The brick and smaller board make a lever to hold the forms close.
The bottom foto is how one of the neighbors brings out water from his place because the street water has been shut off for two days. Like siphoning gas out of a car, we suck on the hose and get 55 gallons mas o menos.
A couple of windows in front and more second level walls
Forms for the castillos (upright beams)
The neighbor brings water needed to mix mortar House building in Pinal Villa, Costalegre, Mexico
Wednesday, October 22, 2008
Week Four - Starting on the walls
We finally got some clay brick but started with cement block just so they could go to work. Both bricks are nearly the same size. There is a regular brick and an over-sized. We're using the larger which will use less cement and go up faster - the problem is they are not as easily found and do cost more. The first section laid is a meter high so the weight does not compress the wall. One meter is also the standard window height
The bottom foto shows how when working with block, they insert a few rows of clay brick because clay is more flexible and will relieve earthquake stress on the walls.
The bottom foto shows how when working with block, they insert a few rows of clay brick because clay is more flexible and will relieve earthquake stress on the walls.
From lot next door
Mixing the bricks
Example from other construction - A few rows of clay brick for stress reliefBuilding a house in Pinal Villa, Costalegre, Jalisco
Labels:
block,
brick,
casa,
cement,
clay,
earthquake,
Pinal Villa,
stress