Wednesday, January 29, 2014

Earth bag construction on the Costalegre

The builder and others also call it Adobe Bag and Superadobe construction but I'm not sure you couldn't use any clean dirt, either moist or dry. Nobody went into any detail on what constitutes Adobe ... as in; mud, clay, straw, fiber, etc. Lot's of sites and pages on this kind of construction "out there" so we'll find the best answers when the actual time comes. Personally I'd love to buy an adjoining lot to mine and experiment with things like this and a real vegetable garden.

The casita builder below has a screen name of Mazinka and lives in or near La Manzanilla north of us in Melaque.  He just suggested that the fill earth should have a certain amount of clay and sent this link - What is Super Adobe .  The video on the bottom just has some ideas for something similar but I much prefer the palapa roof and other local ideas.   Stucco or mortar directly to plastic does not sound secure and I would definitely try to attach chicken wire like they do on old Adobe restorations.






Sunday, May 3, 2009

Front gates installed

The front gates were installed yesterday and only the two front window bars remain for next week. They came late on Friday to install but we are only setup for 110 volts and their welder is 220v. Yesterday they climbed the wall and hooked directly to the incoming lines giving them the 220v.

Definitely not the strongest protection in the world but we can always beef it up later. This will work to deter people with a minor interest in looking around but there will be little there to see - kids have used it as a playground.

I've been moving the stacks of brick and block over to the side so we can level the lot and cover the septic. Still have to move a large pile of gravel and then a much larger pile of dirt .... so will probably enlist a neighbor for that. I want the lot level with a slight slope towards the street before the rains. Not ready for turf yet so may bring some grass seed to hold things together

I think on the last post I called the fencing material Maya Ciclon but on the ferretería bill it was called Malla Ciclon. Pronounced the same but interesting

Installers putting in the last section

Complete from the outside

Added the window bars this morning (the 5th)

Villa Pinal, Melaque, Costalegre

Saturday, February 7, 2009

Cistern patio and walls - Week seventeen

The top of the cistern would have made a huge table but at only knee high we would have had to excavate for seating. Nope wasn't gonna work so I asked them to make a rectangle we could use it as a small patio - covered someday. Here they are blending the rectangle top with the circular one.

The bottom foto is the foundation for the lot sidewall. Just ordered another 1000 blocks for the front wall foundation and the septic tank.

Cistern patio from the corner of the lot

Sidewall foundation

Construction of small house in Pinal Villa, Costalegre

Thursday, December 11, 2008

Semana Diez para la Casa

Updates may be every two weeks but we will see. Putting up walls is only so interesting. Last week we finished the walls to roof level and installed a support beam across the larger front room. This week we've started on the second stage of walling off the back of both lots, stairs and a wash-utility-storage area. I have no exact measurements for this utility area so we will wait for walls and when the dirt is removed, mark it out. The jog that you can almost see in the second foto is because both lots are not the same size

Roof support beam for the large room

Second stage foundation

Second stage from roof level

Retired and building a small house in Villa Pinal, Costalegre, Jalisco Mexico

Sunday, November 23, 2008

Week Eight - Walls up to three meters

This week we are starting on the top level of the walls up to the future roof level. The wall on the left is about 12 centimeters higher than the wall on the right for water runoff. You can't allow water to drain into your neighbors yard if you are on the lot line - and we are on the lot line on two sides.

We had to build an A-frame scaffold for solid support when working 3 meters up. I also bought a 2x10 by 10 feet to use as a platform. The thin 1x8 palm boards used for cement forms were not stable enough.

View from back neighbors lot

View of one bedroom - A-Frame scaffold partly shown


Building a small house in Pinal Villa, Costalegre

Tuesday, November 11, 2008

Weeks Six and Seven

They finished the walls to the two meter level and now it's time to tie it all together with a cement header (dala) all the way around. Today they will finish pouring the header on the two rooms in the back .... and them on to the front two rooms. We're also putting some of the electrical tubing in the dalas so the roof installation will have a few less to do. The routing of the wires is not what I would have chosen but unless I'm there all day to check ... and I've been feeling under the weather this week. Anything can be re-done by chipping away the cement and brick and that's what they rely one.

Beginning of week Six

Toward end of week Six

Week Seven and dalas (headers) are started

Rebar for dalas almost in place and cement forms starting

I added this foto from the end of week seven to show the headers with forms off

Building a small house on the Costalegre, Jalisco Mexico

Sunday, November 2, 2008

The roof maze

This is the maze we are going to deal with someday when we put on the roof. The foto below is of a soon to be multi-story so we'll have no plumbing extending up - but all the electric will be in the ceiling. Most plumbing in Mexico is also on the roof because that is where your water storage tank is unless you have a pressure system. The foam is both to lighten the load and to better insulate from the sun. The orange tubing is where the electrical wires are run - after


Building a house in Pinal Villa, Costalegre, Jalisco

Wednesday, October 15, 2008

Building the foundation - Week Three

Week three. They finished up the dalas and added foundation walls and dalas for three bathrooms. We then needed fill inside the foundation to put the slab on. They couldn't find anyone they knew that would deliver so I went out yesterday and talked to a guy on the carretera. He was a little vague at first when he could do it but showed up an hour later with his 'tractor'. He leveled out and moved what dirt we had into the house and a half hour later the BIG truck showed up - three loads total.

The dirt (arena) is from Aguacate and looks like sand but has clay in it that compacts well. There are a few large pieces in it that are cement stone like but break up easily. This stuff is what is normally used below a slab. We ended up with about a 1/2 truck extra and will have to use it elsewhere.

Can't spread it out over the yard as it will make terrible soil for a garden. 3 truck loads and the tractor for half a day was $2500 pesos.


Double load

The tractor

Foundation is full - with watering or rain it will compact

Pinal Villa, Costalegre, Jalisco

Tuesday, October 14, 2008

Building the foundation - Week Two

Our first albaniel turned out to be fast but very little thought was going into what he was doing. There were not enough support columns (castillos) for our spans and bathrooms were not planned. We added 7 new columns - 5 down the middle and two on either side of the large front room.

The bottom foto is of the reinforced 'header' (dala) that goes above the block, the top of which will be the floor level. I rented the wood for forms but will buy some next time as we'll use them multiple times.

Adding the extra castillos

The dala - header

Building a house in Pinal Villa, Costalegre, Jalisco

Sunday, October 12, 2008

Our lots in Pinal Villa, Melaque

These are fotos of our lots in Pinal Villa about a mile back from the beach and directly behind Melaque. I looked for lots for over a year and was about 2-3 years late to find real bargains. Prices closer to the beach doubled and tripled in that amount of time. Even though there were a number of lots in our price range back from the beach, many didn't have water or electricity. Pinal Villa still does not have Telmex (phone) services.

I found the lot in the first foto last winter but the family member of the adjoining lot didn't want to sell at the time. He later called us to see if we were still interested.

The two people sitting in the back of the first foto are Canadians who own three lots behind us and are building two casitas. They only plan to work on their place during the winter and I'm not sure they will finish this year.

The lots last winter with Canadians sitting on lot behind


Costalegre, Jalicso, Mexico

Thursday, September 25, 2008

Building a house in Mexico


Building a house in Mexico
A small place in Pinal Villa, Costalegre

Pinal Villa is a small community about a mile behind Melaque, Jalisco on the Costalegre, Mexico.

I bought the first of two lots in November of 2007 and the second adjoining lot in the summer of 2008. What we paid is less important than to say they were equal to less developed lots that had no water or electricity and no neighbors to share the costs.

I've learned a lot and am still learning - but the first lesson was to fence and mark your lot well because the Ejido will just go by fence lines and ignore what your original paperwork says. We lost almost three feet off the back and a foot or two on one side. Many of the lots in Pinal Villa are un-plotted (not on a map) so had to be re-measured.

The cost of title transfer is only per square meter and doesn't matter if there is a house or vacant lot. For us it was about $2500 pesos. If the previous owner has not paid taxes or have receipts you need to pay the last 5 years - $100 pesos a year.

Building in Pinal Villa Web Page