The columns are up still in the cardboard tubes. They say it doesn't matter when you remove the tubes because the cement shrinks as it ages making it easier. I had them cut off almost a foot and a half from the tops today as the outside edge was just too high and would give less rain protection. Also thinking it would look better lower. For something this heavy (20 sq meters of cement) it has to attach to the re-bar in the roof so height adjustment is not totally flexible. The old marquesina is only a foot wide and made of Styrofoam panel. This will be over 4' wide
With the new angle we're talking about using curved tiles instead of flat over the cement. I really like the look of curved tiles but you can't walk on them if you need to paint or work above. Only the bottom edge of curved tiles are cemented down so maybe the uppers can be moved for access. Next week is renting a machince to cut into the roof and it's rebar and rent some staging so they can work safely 3 meters up.
Foundation footing
Columns in place