Thursday, March 12, 2009

I guess this is week 21

We have just been finishing up walls around the lots so not much there. My albañil fell off the scaffolding on Monday from 2 meters up. Nothing broken but scraped and bruised. Doctor told him to take 3 days off and we've since decided the whole weeks rest is better.

Next week we will be working on the electric pole, the support castillo, meter base, a breaker and plug. If we have time will start on the septic and drainage lines

The septic (fosa septica) will look something like this

0 comments: